Risk identified as Balcony alongside the boxing in 

We agree to board up – safer and warmer and also breaks the place into zoned areas

A storage room is created behind the ball launcher and a framework built on the existing balcony to house plasterboards

Volunteer Oscar joins us for a day to advise and stays 3 weeks! (on ay home from work)

Aug 2024

Over August he boards the balcony area | Ceiling, and both sides 

Both end of August the whole area is plastered 

Sept 2024

In September the Paint Volunteers move in  – first wallop

In middle of September our Electrician adds Light and we measure for carpet out of our acquired stockpile 

Oct 2024

October – Volunteer professional but unpaid decorator Des back on site as wants the doors looking right .